Element of Constructive Acceleration: Contractor gives Owner _____ _____ of the delay and a proper request for a time extension.

Enhance your knowledge with the DBIA Exam 3 quiz. Tackle DBIA-related questions using flashcards and multiple choices with detailed explanations. Prepare thoroughly for your upcoming exam!

Multiple Choice

Element of Constructive Acceleration: Contractor gives Owner _____ _____ of the delay and a proper request for a time extension.

Explanation:
In constructive acceleration, the contractor must promptly alert the owner about delays and formally request an extension of time. The term “timely notice” captures the critical timing element: the delay must be reported within the window the contract requires, and the request for a time extension must follow the contract’s procedures. This combination preserves the contractor’s right to remedies for delay and helps the owner assess impacts on the schedule. If notice is late or informal, the contractor risks waiving the right to an extension or to recover time-related costs. Verbal notice or no notice wouldn’t meet the contract’s formal requirements or timing, and simply saying a delay exists without a proper, timely extension request wouldn’t satisfy the element needed for constructive acceleration. Written, timely notification plus a proper extension request gives the owner the information and process needed to adjust the schedule or compensate for the delay.

In constructive acceleration, the contractor must promptly alert the owner about delays and formally request an extension of time. The term “timely notice” captures the critical timing element: the delay must be reported within the window the contract requires, and the request for a time extension must follow the contract’s procedures. This combination preserves the contractor’s right to remedies for delay and helps the owner assess impacts on the schedule. If notice is late or informal, the contractor risks waiving the right to an extension or to recover time-related costs. Verbal notice or no notice wouldn’t meet the contract’s formal requirements or timing, and simply saying a delay exists without a proper, timely extension request wouldn’t satisfy the element needed for constructive acceleration. Written, timely notification plus a proper extension request gives the owner the information and process needed to adjust the schedule or compensate for the delay.