_____ actually accelerates its performance, thereby incurring excess costs.

Owner

Architect

Subcontractor

Contractor

The party most likely to accelerate the work is the contractor, because they control field execution, sequencing, and how resources are allocated. When a schedule is tight or a deadline is at risk, the contractor may deploy additional crews, run overtime, bring in equipment sooner, or order materials on an expedited basis to speed up progress. All of these actions add costs beyond the original plan, creating the excess costs referenced. The owner may influence or approve acceleration and cover any premium, but the actual decision to speed up and the execution of that acceleration come from the contractor. The architect and subcontractors play important roles in design and specialized work, respectively, but they don’t drive schedule acceleration or bear the primary cost impact in these scenarios.

Next question

Find the option that is right for you!

All options are one-time payments.

$12.50

30 day premium pass

All the basics to get you started

  • Ad-free experience
  • View your previous attempt history
  • Mobile app access
  • In-depth explanations
  • 30 day premium pass access
$30.00 $87.50 usd

6 month DELUXE pass (most popular)

Everything with the 30 day premium pass FOR 6 MONTHS! & the ultimate digital PDF study guide (BONUS)

  • Everything included in the premium pass
  • $87.50 usd value for $30.00! You save $57.50!
  • + Access to the ultimate digital PDF study guide
  • + 6 months of premium pass access
  • + Priority support
$12.50 $18.99

Ultimate digital PDF study guide

For those that prefer a more traditional form of learning

  • Available for instant download
  • Available offline
  • Hundreds of practice multiple choice questions
  • Comprehensive content
  • Detailed explanations
Image Description
Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy