An Implementing technique for Execution recommends the Design-Builder and its team to establish and maintain a _____ system.

Enhance your knowledge with the DBIA Exam 3 quiz. Tackle DBIA-related questions using flashcards and multiple choices with detailed explanations. Prepare thoroughly for your upcoming exam!

Multiple Choice

An Implementing technique for Execution recommends the Design-Builder and its team to establish and maintain a _____ system.

Explanation:
In execution, having a schedule system as the central control tool keeps the design-build team aligned on when things must happen. It ties together design development, procurement, and construction activities, laying out the sequence of work, key milestones, and the critical path. With this system, progress can be tracked, forecasts updated, and decisions made to keep the project moving toward the target date. It also helps owners, designers, builders, and subs see how changes affect timing, so resources and sequences can be adjusted proactively to avoid delays. Other options don’t fit as the primary execution control: a trend-tracking system is useful for looking at performance over time but isn’t the main mechanism for controlling work flow; a risk-management system is about identifying and mitigating potential issues, which complements execution but is not the primary delivery-control system; a ledger is about financial accounting, not the sequencing and timing of project activities.

In execution, having a schedule system as the central control tool keeps the design-build team aligned on when things must happen. It ties together design development, procurement, and construction activities, laying out the sequence of work, key milestones, and the critical path. With this system, progress can be tracked, forecasts updated, and decisions made to keep the project moving toward the target date. It also helps owners, designers, builders, and subs see how changes affect timing, so resources and sequences can be adjusted proactively to avoid delays.

Other options don’t fit as the primary execution control: a trend-tracking system is useful for looking at performance over time but isn’t the main mechanism for controlling work flow; a risk-management system is about identifying and mitigating potential issues, which complements execution but is not the primary delivery-control system; a ledger is about financial accounting, not the sequencing and timing of project activities.